Enhancing industrial efficiency in an integrated lot sizing and scheduling problem
Manufacturing Engineering Laboratory of Tlemcen (MELT), University of Tlemcen, BP 230 Tlemcen, Algeria
* Corresponding author: This email address is being protected from spambots. You need JavaScript enabled to view it.
& This email address is being protected from spambots. You need JavaScript enabled to view it.
Received:
1
January
2025
Accepted:
6
April
2026
Abstract
This study investigates an integrated production planning and scheduling problem within a complex industrial environment featuring non-identical parallel production lines. It focuses on reducing the impact of downtime, which incurs substantial setup costs. To this end, we introduce advanced transition mechanisms between production periods, motivated by real-world industrial practices, such as setup carryover and setup crossover, in order to enhance inter-period coordination, reduce operational disruptions, and improve overall system efficiency. A mixed-integer mathematical formulation is developed and solved using CPLEX for medium-scale instances, while a Simulated Annealing metaheuristic is designed to handle large-scale cases. The proposed solution framework yields realistic and cost-efficient plans that jointly minimize downtime-related costs, setup costs, production costs, and inventory holding costs.
Mathematics Subject Classification: 35L05 / 35L70
Key words: Production planning / lot sizing / scheduling / transitions between periods / metaheuristics
© The authors. Published by EDP Sciences, ROADEF, SMAI 2026
This is an Open Access article distributed under the terms of the Creative Commons Attribution License (https://creativecommons.org/licenses/by/4.0), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.