Single Machine Preemptive Scheduling to Minimize the Weighted Number of Late Jobs with Deadlines and Nested Release/Due Date Intervals
1
Institute of Engineering Cybernetics,
National Academy of Sciences of Belarus, Minsk, Belarus.
2
Otto-von-Guericke University of Magdeburg, Germany.
Received:
October
1999
Accepted:
November
2000
This paper is devoted to the following version of the single machine preemptive scheduling problem of minimizing the weighted number of late jobs. A processing time, a release date, a due date and a weight of each job are given. Certain jobs are specified to be completed in time, i.e., their due dates are assigned to be deadlines, while the other jobs are allowed to be completed after their due dates. The release/due date intervals are nested, i.e., no two of them overlap (either they have at most one common point or one covers the other). Necessary and sufficient conditions for the completion of all jobs in time are considered, and an O(nlogn) algorithm (where n is the number of jobs) is proposed for solving the problem of minimizing the weighted number of late jobs in case of oppositely ordered processing times and weights.
Mathematics Subject Classification: 90B36
Key words: Single machine scheduling / release and due dates / deadlines / number of late jobs.
© EDP Sciences, 2001
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.