A novel distributed decision-making method for project portfolio risk response considering differences in decision-maker perspectives
1
School of Management, Northwestern Polytechnical University, Xian 710129, P.R. China
2
Centre for Research on Risks and Crises, Ecole des Mines, ParisTech, PSL University, Paris 75006, France
3
Department of Energy, Politecnico di Milano, Milan 20133, Italy
* Corresponding author: This email address is being protected from spambots. You need JavaScript enabled to view it.
Received:
28
July
2024
Accepted:
24
January
2026
Abstract
Risk response is an important measure for ensuring success of a Project Portfolio (PP). To address the limitations of the existing centralized decision-making for PP risk response, a new distributed decision-making method for PP risk response is proposed. Initially, a comprehensive risk interaction evaluation method is proposed integrating Interval Neutrosophic Sets (INSs) and Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) along with Decision-making Trial and Evaluation Laboratory (DEMATEL). Subsequently, project risk interaction evaluation in different scenarios of Project Decision-Maker (PDM) is defined. The methods for the comprehensive evaluation of risks from the perspectives of PDM and of PP Decision-Maker (PPDM) are also given. Following this, a bi-level programming model is constructed in which the decision-maker of the upper layer is PPDM and that of the lower layer is PDM. A case study is conducted on a display Research and Development (R&D) PP to validate the feasibility of the method. The results of the case study show that PP Risk Response Decision (PPRRD) can be affected by different scenarios of PDM and the hierarchical model can effectively resolve conflicts caused by differences in decision-making perspectives between PPDM and PDM.
Mathematics Subject Classification: 90b50 / 90C70
Key words: Project portfolio / risk response / distributed decision / bi-level programming / DEMATEL
© The authors. Published by EDP Sciences, ROADEF, SMAI 2026
This is an Open Access article distributed under the terms of the Creative Commons Attribution License (https://creativecommons.org/licenses/by/4.0), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.