Integration of parts scheduling, MRP, production planning and generalized fixed-charge transportation planning in the design of a dynamic cellular manufacturing system
1
School of Industrial Engineering, College of Engineering, University of Tehran, Tehran, Iran
2
Department of Logistics, Tourism, & Service Management/Faculty of Business & Economics, German University of Technology (GUtech), Muscat, Oman
3
Department of Industrial Engineering, Firoozkooh Branch, Islamic Azad University, Firoozkooh, Iran
4
Department of Industrial Engineering, Birjand University of Technology, Birjand, Iran
5
Department of Industrial Engineering, Urmia University of Technology, Urmia, Iran
* Corresponding author: reza.kia@gutech.edu.om
Received:
9
November
2017
Accepted:
11
June
2020
In this paper, to integrate the decisions of parts scheduling, Material Requirement Planning (MRP), Production Planning (PP) and Transportation Planning (TP) for designing a Cellular Manufacturing System (CMS) under a dynamic environment, a Mixed-Integer Nonlinear Programming (MINLP) mathematical model is formulated. The proposed mathematical model integrates extensive coverage of significant manufacturing characteristics in designing a CMS to be implemented in a three-layer supply chain. The considered features include markets demands, heterogeneous vehicles, raw materials requirements planning, parts due dates, cell size limits, machines capacity, intra/inter cell material handling time/cost, transportation time/cost, operation time, alternative processing routes in addition to the main decisions of parts scheduling, PP, TP and dynamic cell formation. Also, some novel characteristics are incorporated based on a three-layer supply chain that make the presented model remarkable respect to the literature including (1) In the first layer, planning the orders of raw materials with different lead times and usage coefficients is performed, (2) In the second layer, decisions of dynamic cell formation and parts scheduling are made, and (3) In the third layer, optimal vehicles are selected as a generalized fixed-charge TP based on transportation time and cost to satisfy multi-markets with different demand volumes. The components in the objective function to be minimized include total costs of holding the parts inventories in the markets, backorders, tardiness, transportation of the parts from the plant to the markets, purchase of raw materials, keeping raw materials in the plant warehouse, intercellular/intracellular movements and machine relocation. An illustrative numerical example is solved by the CPLEX solver to illustrate the achievements obtained by the incorporated characteristics in the integrated model. Furthermore, a sensitivity analysis is performed to assess the effects of important parameters on the model performance. Since the proposed model is NP-hard, a Simulated Annealing (SA) algorithm is improved by an elaborately-designed matrix-based chromosome representation is applied to represent all decision variables, as well as a sequential procedure generating initial solutions. Several test problems either generated randomly or taken from the literature with various sizes are solved and the results are compared with the solutions gained using CPLEX solver. The comparisons results show that the designed SA is capable of evolving optimal or near-optimal solutions with reasonable relative gaps in a computationally satisfactory manner.
Mathematics Subject Classification: 90-10
Key words: Dynamic cellular manufacturing system / three-layer supply chain / scheduling / production planning / transportation planning
© EDP Sciences, ROADEF, SMAI 2021
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.